TAILINGS MANAGEMENT Program
Tailings are finely ground natural rock residue from the processing of
mineralized ore by physical grinding and flotation methods used in our
operations. PT Freeport Indonesia uses a river system for tailings transport to
a designated area in the lowlands and coastal zone, called the Modified Ajkwa
Deposition Area, which is an engineered, managed system for the deposition and
control of tailings.
The tailings deposition system is operated under PT Freeport Indonesia's
comprehensive tailings management plan, as approved by the Government of
Indonesia. The first stage of construction of the lateral containment
structures, or levees, for the deposition area was completed in 1997. The second
stage of construction work, including an extension of the levees, was completed
in 2002. Work is continually conducted on various enhancements to the system,
including inspections, monitoring and physical works.
We continually evaluate and update the tailings management plan to minimize
potential risks. PT Freeport Indonesia conducted comprehensive technical
evaluations of alternative tailings disposal options using internationally
recognized scientific experts and adopted the most appropriate site-specific
management system. Independent environmental audits of PT Freeport Indonesia's
environmental management system concluded that the company's tailings management
plan represents the best alternative, considering the applicable geotechnical,
topographic, climatological, seismic and water quality conditions.
|